Tennova Healthcare Cleveland Hybrid Operating Room Renovation

Cleveland, TN

We Are Building

This was a 2,375 sf renovation of equipment storage space to include a hybrid operating room, one-hour storage room and support space. The project included installation of a supplemental HVAC to the existing air handling unit (AHU), which involved installing a pre-treat unit within the air plenum of the existing AHUs.

Features and Facts

The project was successfully completed 3% under initial project budget. 

There were extensive MEP systems above the ceiling and deck height. Messer worked collaboratively with the architect to create solutions that allowed the rating to stop at ceiling and create a one-hour rated box.

Assignment: Construction Manager

Architect: TMPartners

Mechanical Engineer: Envision Advantage