New Manufacturing Facility and Expansion - Aisin Automotive Casting, Inc.
Clinton, TN
Features
- Phase I was a fast-track design/build project with substantial completion scheduled for approximately seven months from ground breaking.
- This tight schedule could only be met through the effective use of Lean Construction tools. Messer’s ability to develop an effective Reverse Phase Schedule enabled us to meet this challenging schedule.
- Phase I was occupied throughout construction of Phase II. A divider wall was used to separate Phase I so it could continue daily operations without interruption from construction activities.