Civil and Plating Line Expansion and Addition - Siemens Energy, Inc.
Roebuck, SC
Features
- Messer worked hand-in-hand with Siemens to ensure zero disruption to production during the expansion.
- Utilized Digital Twin, resulting in schedule benefits and a total cost avoidance of $1 million.
- Leveraging 3D BIM enabled improved visualization of functionality, refined PALM equipment general arrangments, elimination of granted platform, reduced extent of framing to equipment and a total cost avoidance of $80,000.
- Implemented "Siemens First" philosophy, which resulted in a schedule acceleration of two weeks and a total cost savings of $200,000.